Kv Eldaren
Project: New building
Our delivery: 2010
- Steel structures & installation for 500 m long bridge
Partners:
- Investor: Tiehallinto
- Main contractor: Skanska Infra Oy
- Designer: Ramboll Finland Oy
- Steel structures & installation for 500 m long bridge
- Ruukki’s new installation technology will considerably speed up installation; Bridge sections will be lifted directly into place by sea crane and welded together
- Total steel structure installation time on site will be cut from half a year to just one month compared to conventional construction methods
- Largest bridge sections ever made for Finnish bridge, each section is 100 meters long and weigh 200 tonnes.